1. Survey
  2. Design
  3. Fit
  4. Commission
  5. Costs
  6. Rules

Independent installation guide

How a heat pump is installed

The four stages of an installation in the order they happen, with the deadlines the grant puts on each one and the points where a homeowner has to act.

Figures checked 3 November 2026Sources at the foot of the pagePublished by SEO-DONS LTD, an independent guide

Fitting a heat pump is less like swapping a boiler and more like a small building project. It has a design stage, an approval stage and a hand-back, and if the grant is involved, it runs against a clock. Knowing the order lets you spot when something is being skipped.

Timeline of a grant-funded installation: quote accepted, Ofgem emails you with 14 days to confirm, voucher issued, 3 months for air source or 6 for ground source to install and commission, voucher claimed.
Ofgem property owner guidance v5.1; GOV.UK. Checked 3 November 2026.

Stage 1: the survey

Everything starts with someone measuring the house. A proper survey works out how much heat each room loses on a cold day: through walls, windows, roof and floor, and through draughts. Those room figures add up to the heat the whole house needs, which sets the size of the heat pump. Installers certified by MCS design to the MCS heat pump design standard, MIS 3005-D.

The visit is also when the installer looks at where the outdoor unit could go, where a cylinder would fit, how the pipes would run, and what the electricity supply looks like. A quote produced without a visit, or without heat-loss figures, is a guess. Our heat-loss survey page covers what to expect from it.

Stage 2: design, quote and the grant application

The survey becomes a design: the unit's size in kilowatts, the design flow temperature, which radiators stay and which grow, the size and position of the cylinder, and the controls. The quote should be built from that design and list each part, with the grant shown as a deduction. Ofgem expects the quote to be clear and itemised.

When you accept, the installer applies for the grant on Ofgem's system. Ofgem then emails the property owner to check that the installer is acting for them. You have 14 days to confirm, and if you do not, the application can be rejected. Ofgem may also phone or visit, and MCS may run its own checks.

If the outdoor unit cannot meet every permitted development condition, this is also the stage for a planning application: for example a unit bigger than 1.5 m³, a second unit on a semi-detached house, or a site on a wall facing a road in a conservation area. The planning permission page lists every condition.

Stage 3: the fitting

Once Ofgem issues the voucher in the installer's name, the clock starts: 3 months to install, commission and claim it for an air source heat pump, 6 months for ground source. Inside that window, the fitting usually covers:

  • The outdoor unit on a solid base or wall brackets, in the spot the design and the sound check allow, with room left around it for air and servicing.
  • The pipe run from the unit through the wall to the heating circuit, insulated outside.
  • The cylinder, and a buffer tank where the design needs one, usually in an airing cupboard, loft or utility space.
  • The radiators the design says must change, and new controls.
  • The electrics: a supply to the unit, and the network operator either notified afterwards or asked first, depending on the home's new maximum demand.
  • The old boiler taken out, with whatever it leaves behind made safe.

For ground source, the ground works come first: trenches for a horizontal loop or a drilling rig for boreholes. That is the main reason the voucher allows longer. See ground source installation.

The heating and hot water will be off for part of the fitting. Ask for the days in writing before work starts, especially in winter.

Stage 4: commissioning and the claim

Commissioning is the switch-on done properly: the system filled and checked, the controls set up, readings recorded. The installer then registers the installation with MCS, which produces the MCS certificate, and claims the voucher from Ofgem. The grant is already off your bill at that point; the claim is between the installer and Ofgem.

Before the final payment you should be handed the paperwork: the MCS certificate, the commissioning record, the design figures, building regulations paperwork and warranties. The commissioning and handover page lists each one and why it matters later.

What can push the dates back

Three things regularly add time, and each is easier to plan for than to discover halfway through:

  1. A planning application. Needed when any permitted development condition fails. It belongs before the fitting, so build it into the schedule.
  2. The electricity supply. Where the home's new maximum demand is between 60A to 100A, the installer must apply to the network operator before fitting, and the operator assesses it within 10 working days. If the supply needs upgrading, that is extra time and possibly cost. See heat pump electrics.
  3. Ground works. For ground source, access for diggers or a drilling rig, and the weather, set the pace.

None of these extend the voucher. If a delay looks likely, raise it with the installer early: a voucher that lapses cannot be claimed.

Fitting before applying

Some installations go ahead before a grant is applied for, for example after a breakdown in winter. The scheme allows a retrospective application, but it must be properly made within 120 days of commissioning, and Ofgem's guidance warns that the owner carries extra risk: if the application fails, there is no grant. Only the installer can ask Ofgem to review a decision, within 28 days.

If you are weighing this up, ask the installer in writing what they will charge if the grant is refused. For the amounts and who qualifies, see the cost page, which states the grant of £7,500 with its conditions.

Questions about the process

How many days will installers be at my house?

No official source publishes a typical number of days on site, and it varies with the radiator work, the cylinder and the pipe run. Ask each installer for a written day-by-day schedule, including how long the heating and hot water will be off.

Can work start before the grant is approved?

It can, but the risk moves to you. A retrospective application must be properly made within 120 days of commissioning, and if Ofgem refuses it you pay the full price. Most people wait for the voucher.

What happens if the installer misses the voucher deadline?

The voucher expires: 3 months after issue for air source, 6 months for ground source, and the grant cannot be claimed against it. Agree a schedule that fits well inside the window, and ask what happens if a delay is on their side.

Who tells the electricity network about the heat pump?

The installer. Depending on the home's new maximum demand, they either connect and then notify the network operator within 28 days, or apply before fitting. See our guide to heat pump electrics.

Where this page's figures come from

  1. Ofgem, Boiler Upgrade Scheme for property owners
  2. Ofgem, property owner guidance v5.1 (PDF)
  3. GOV.UK, Boiler Upgrade Scheme: how to apply
  4. MCS, notifying network operators (DNOs)
  5. legislation.gov.uk, permitted development Class G

Read on 3 November 2026. Rules and statistics change: if anything here disagrees with the official page, the official page is right. Tell us through the form and we will correct it.

Got a question about your own installation?

Describe the house and where you are in the process: no quote yet, a quote to make sense of, or a voucher already issued. The message goes to SEO-DONS LTD, the company that publishes this guide, and a reply comes back by email.

What happens next

  1. SEO-DONS LTD, the publisher of this guide, receives your message.
  2. We answer by email, using the official figures and rules this site is built on.
  3. You decide what to do next. Sending a question does not sign you up to anything.
Tell us more about the house (optional)

Your message is read by SEO-DONS LTD, publisher of Heat Pump and Installation, and answered by email. This site does not fit, survey or sell heat pumps and does not run any grant scheme. See our privacy notice.

Ask a question
Ask a question