Independent installation guide

Installing a ground source heat pump

A ground source heat pump is a bigger project than air source: the heat comes from pipes buried in the garden or sunk in boreholes. What the ground works involve, what the official prices show and how the timetable changes.

Figures checked 3 November 2026Sources at the foot of the pagePublished by SEO-DONS LTD, an independent guide

Inside the house, a ground source heat pump looks much like any other heating system: a unit, usually indoors, connected to a hot water cylinder and the radiators or underfloor heating. The difference is outside. Instead of a fan unit drawing heat from the air, a sealed loop of pipe buried in the ground carries a fluid that collects heat from the soil or rock and brings it to the heat pump.

How the system is laid out

There are three parts. The ground loop, buried outside, with a manifold where its pipes join. The heat pump itself, which needs a space indoors or in an outbuilding. And the heating side, which is the same as for air source: a cylinder for hot water and emitters sized to a design flow temperature. Because there is no outdoor fan unit, there is no outdoor unit to site against the Class G rules, but there is a lot of ground to reinstate.

Two ground loop layouts: a horizontal loop in trenches across open ground, and vertical loops in boreholes drilled by a rig.
Schematic, not to scale.

Trenches or boreholes

A horizontal loop is laid in trenches dug across open ground and then backfilled. It needs a wide area that can be dug up and reinstated, and access for a digger. Where the land is there, it avoids the cost of drilling.

A vertical loop goes down one or more boreholes. It takes much less surface area, which suits smaller plots, but it needs a drilling rig on site and the ground below to be suitable for drilling. The number and depth of boreholes come from the design, which works back from the heat the house needs.

Either way, the loop is sized from the same heat-loss calculation as an air source system, so the survey comes first. The design then has to show where the loop goes, how much of it there is and how the ground will be left.

What a ground source installation costs

Far fewer ground source systems are installed under the grant than air source, so the official figures move a lot between quarters. Use the yearly figure as the steadier guide:

Median installed price of grant-funded ground source heat pumps, England and Wales (DESNZ)
PeriodMedian priceAfter £7,500
April 2025 to March 2026 (sample of 365)£26,500£19,000
April to June 2026£27,232£19,732
July to September 2026£34,630£27,130

In the latest quarter, half of ground source jobs cost between £22,348 and £53,345, and the median size was 15 kW, almost twice the 8 kW median for air source. Bigger systems explain part of the price gap; the ground works account for much of the rest. For comparison, the median air source job in the same quarter was £12,826; the cost planner covers both.

These prices include VAT and, according to DESNZ, the grant value. Installing a ground source heat pump in a home is zero-rated for VAT until 31 March 2027, then 5%.

The grant is the same £7,500 as for air source, for owners replacing fossil fuel or electric heating through an MCS certified installer. A home with no mains gas connection replacing oil or LPG can get £9,000 instead, for applications properly made by 31 March 2027.

The timetable

The grant's clock is longer for ground source: once the voucher is issued, the installer has 6 months to install, commission and claim it, against 3 for air source. Regulations also stop ground source vouchers running past 31 March 2030. The earlier steps are the same: the installer applies, and you confirm within 14 days of Ofgem's email.

Within that window, the ground works usually come first, then the indoor connection and the heating-side changes, then commissioning. Weather and access for machinery affect the pace of the ground works more than anything else, so agree a schedule with some room in it. The installation stages page sets out the order.

Planning

In England, installing, altering or replacing a ground source heat pump within the grounds of a house or block of flats is permitted development under Class C, and water source under Class D. Unlike air source, the text sets no limit on size or number. A listed building, or other protected sites, needs a conversation with the council. See the planning permission page for the air source rules alongside.

What the design should show

  • The heat-loss figures and the heat pump's size in kW.
  • The loop type, its length or the number of boreholes, and where it runs on a site plan.
  • How the ground will be reinstated, and who does it.
  • Where the heat pump sits indoors, and the space it needs.
  • The cylinder, the emitters and the design flow temperature.
  • A schedule that fits inside the 6-month voucher.

At the end, the handover should include the ground loop's layout alongside the usual papers, because anyone digging in that ground later will need it. The handover page lists the rest.

Ground source questions

Is a ground source heat pump worth the extra cost over air source?

This guide does not judge that for you, because it turns on running costs and your own site. What the official figures show is the installed price gap, and what the ground works involve. If you are weighing both, get both designed from the same heat-loss survey so the comparison is like for like.

Do I need planning permission for a ground source heat pump?

In England, installing a ground source heat pump within the grounds of a house or a block of flats is permitted development under Class C, and the Part 14 text sets no size limit for it. Listed buildings and other protected sites need checking with the council.

How long does the grant give me for a ground source job?

6 months from the voucher being issued to install, commission and claim it, twice the 3 months for air source, because of the ground works. Vouchers for ground source also cannot run past 31 March 2030.

Can neighbours share a ground loop?

Yes, shared ground loops serving several homes exist, and the grant has a separate capacity limit for them of 300 kWth. They are a bigger project with their own agreements, so ask an installer who has designed one.

Where this page's figures come from

  1. DESNZ, Boiler Upgrade Scheme statistics September 2026
  2. Ofgem, Boiler Upgrade Scheme for property owners
  3. GOV.UK, Boiler Upgrade Scheme: what you can get
  4. legislation.gov.uk, GPDO 2015 Schedule 2 Part 14
  5. HMRC, VAT Notice 708/6

Read on 3 November 2026. Rules and statistics change: if anything here disagrees with the official page, the official page is right. Tell us through the form and we will correct it.

Got a question about your own installation?

Describe the house and where you are in the process: no quote yet, a quote to make sense of, or a voucher already issued. The message goes to SEO-DONS LTD, the company that publishes this guide, and a reply comes back by email.

What happens next

  1. SEO-DONS LTD, the publisher of this guide, receives your message.
  2. We answer by email, using the official figures and rules this site is built on.
  3. You decide what to do next. Sending a question does not sign you up to anything.
Tell us more about the house (optional)

Your message is read by SEO-DONS LTD, publisher of Heat Pump and Installation, and answered by email. This site does not fit, survey or sell heat pumps and does not run any grant scheme. See our privacy notice.

Ask a question
Ask a question